Home arrow Home arrow News arrow Consultant error leads to project delay
Advertisement
Consultant error leads to project delay Print E-mail
Written by Diego Abeloos - Staff Writer/diegoa@latc.com   
Wednesday, 28 November 2012

A surveying error by a city-contracted design consultant will likely delay a sewer-main replacement project on Fallen Leaf Lane for three to four months.

Los Altos Public Works Director Jim Gustafson told the Town Crier the error was first discovered by Pacific Underground Construction Inc. (PUC), which determined that a 0.25-mile-long sewer pipe on Fallen Leaf Lane in South Los Altos was too close to an existing 24-inch water transmission line.

As a result, Gustafson said the $1.7 million project – slated for completion in January – may not resume until spring 2013.

Specifically, Gustafson noted that the lines were within a foot of each other – in apparent conflict with design drawings provided by the city’s design consultant – Harris & Associates. The company has since agreed to revise the construction documents at no cost to the city.

However, because of the short distance between the lines, the project required a different method of sewer pipe removal than originally anticipated. According to Gustafson, the project originally called for the sewer pipe’s removal and replacement with a method called bursting – sending vibrations into the ground and using a ramming device to break up and remove piping.

Moving the project forward using the bursting method, Gustafson said, could cause the water line to break.

“We could weaken it and then it wouldn’t be properly supported,” he said.

The project staff report noted that an open-cut trench method is now required to complete the project.

The surveying error by Harris & Associates led the city council to terminate its construction contract with PUC Nov. 13 after city staff and PUC were unable to “negotiate a bilateral change order within the approved project budget,” according to the staff report.

The council, which originally approved PUC’s bid for the South Sewer Main Replacement project in May, authorized a new advertisement for bids on the revised project.

 No Comments
There are no comments up to now.

Post Comment

Email (will not be published)
Name
Title
Comment
 remaining characters
Captcha Image Regenerate code when it's unreadable
We reserve the right to use comments submitted on our site in whole or in part. We will not publish comments that contain inappropriate content, advertising or website links to inappropriate content.
 
< Prev   Next >
Advertisement
Advertisement

Jump to Section

Advertisement

Special Sections

Image

Your Home, Food & Wine, Your Health,
Go Green, On The Road...more

Schools

Image

Local
News
on
Education


People

Image

Engagements, Weddings, Anniversaries, Obituaries



Photo Store

Image

Buy the
photos you see
in our stories
and more

Reader's Corner

Image

Book
Reviews,
News,
and Events